Project Monitoring Schedule | NICAT

Project Monitoring Schedule

National Incubation Centre in Aerospace Technologies Rawalpindi

The Lead partner (Netsole Technologies) shall be responsible for submitting the following report, as per the specified schedule, for the Project.

Name of Report Due Date/Time Status
Pre Incubation Period
  • Project Inception Report
  • Gant Chart of establishment period
  • Procurement Policy & Manual
  • HR Manual
  • Financial & Administrative Policy & Manual
Within -10 days of commencement of project Achieved
  • Completion Report of Establishment of NIC
  • Financial & Internal Audit Report of Establishment phase
Within 30 days after establishment (Y0) of NIC Achieved
1st Year
1st Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
Within 30 days after completion of 1st Quarter of 1st Year Achieved
2nd Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
Within 30 days after completion of 2nd Quarter of 1st Year Achieved
3rd Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
Within 30 days after completion of 3rd Quarter of 1st Year Achieved
4th Quarter: Reports
  • Comprehensive Annual Progress Report
  • Startups Development/Progress Report
  • Annual Financial & Internal Audit Report
  • Annual External Financial Audit Report by A rated Chartered Accountants Firms
  • Startups Feedback/Survey Report
Within 30 days after completion of 4th Quarter of 1st Year Achieved
2nd Year
1st Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
Within 30 days after completion of 1st Quarter of 2nd Year Achieved
2nd Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
Within 30 days after completion of 2nd Quarter of 2nd Year Achieved
3rd Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
Within 30 days after completion of 3rd Quarter of 2nd Year Achieved
4th Quarter: Reports
  • Comprehensive Annual Progress Report
  • Startups Development/Progress Report
  • Annual Financial & Internal Audit Report
  • Annual External Financial Audit Report by A rated Chartered Accountants Firms
  • Startups Feedback/Survey Report
Within 30 days after completion of 4th Quarter of 2nd Year Achieved
3rd Year
1st Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
Within 30 days after completion of 1st Quarter of 3rd Year Achieved
2nd Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
  • Project Mid-Term Review Report
Within 30 days after completion of 2nd Quarter of 3rd Year Achieved
3rd Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
Within 30 days after completion of 3rd Quarter of 3rd Year Achieved
4th Quarter: Reports
  • Comprehensive Annual Progress Report
  • Startups Development/Progress Report
  • Annual Financial & Internal Audit Report
  • Annual External Financial Audit Report by A rated Chartered Accountants Firms
  • Startups Feedback/Survey Report
Within 30 days after completion of 4th Quarter of 3rd Year Achieved
4th Year
1st Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
Within 30 days after completion of 1st Quarter of 4th Year Achieved
2nd Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
Within 30 days after completion of 2nd Quarter of 4th Year Achieved
3rd Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
Within 30 days after completion of 3rd Quarter of 4th Year Achieved
4th Quarter: Reports
  • Comprehensive Annual Progress Report
  • Startups Development/Progress Report
  • Annual Financial & Internal Audit Report
  • Annual External Financial Audit Report by A rated Chartered Accountants Firms
  • Startups Feedback/Survey Report
Within 30 days after completion of 4th Quarter of 4th Year Achieved
5th Year
1st Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
Within 30 days after completion of 1st Quarter of 5th Year Pending
2nd Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
Within 30 days after completion of 2nd Quarter of 5th Year Pending
3rd Quarter: Reports
  • Quarterly Progress Report
  • Startups Development/Progress Report
  • Quarterly Financial & Internal Audit Report
  • Consolidative Impact Assessment Report of previous 2 Years
Within 30 days after completion of 3rd Quarter of 5th Year Pending
4th Quarter: Reports
  • Comprehensive Annual Progress Report
  • Startups Development/Progress Report
  • Annual Financial & Internal Audit Report
  • Annual External Financial Audit Report by A rated Chartered Accountants Firms
  • Startups Feedback/Survey Report
  • Project Completion Report
  • End-line Survey Report
Within 6 months after completion of the project Pending

Note: In addition, on-site monitoring visit conducted by GoP/Project Team or its appointed trusted monitors, as and when needed. A complete project completion evaluation, including Monitoring, Evaluation, and Learning (MEL) report shall also be submitted.