Project Monitoring Schedule
S. No |
Quarter |
Duration |
Report |
Status |
Build-out Phase (Pre- Incubation Period) |
||||
1 |
Y0 Q1 |
Nov 22 – Feb 23 |
Project Inception Report |
Achieved |
Gant Chart of establishment |
Achieved |
|||
Procurement Policy & |
Achieved |
|||
HR Manual |
Achieved |
|||
Completion Report of |
Achieved |
|||
Financial & Internal |
Achieved |
S. No | Quarter | Duration | Report | Status |
| ||||
2 | Y0 Q1 | Nov 22 – Feb 23 | · Quarterly Progress Report | Achieved |
· Startups Development/Progress Report | Achieved | |||
Quarterly Financial & Internal Audit Report | Achieved |
Project Milestones Chart
SR | Quarter | Duration | Milestone | Deliverable | Status |
01
| Y0 Q1 | Nov 22 – Feb 23 | M0.1. Establishment of Incubation Center
| Design document and layout plan
| Achieved |
Provision of Utility Services
| Achieved | ||||
Provision of Furniture
| Achieved | ||||
Provision of Fixtures & Electrical Equipment
| Achieved | ||||
Provision of Fire Safety & Security System
| Achieved | ||||
Provision of AV/Training Lab & Makers Lab Fixtures & Equipment | Achieved | ||||
ICT and other allied Infrastructure & other equipment’s mentioned in project proposal. | Achieved | ||||
M0.2. Development of Project Management Plans and Processes
| Human Resource | Achieved | |||
Mentor / Trainer Engagement | Achieved | ||||
Time Management | Achieved | ||||
Risk Management | Achieved | ||||
Quality Control & Assurance | Achieved | ||||
Communication/Marketing/Outreach/ Promotion plan | Achieved | ||||
Procurement plan | Achieved | ||||
Internal Monitoring & Evaluation (M&E) a) Process Indicators of Program b) Performance Indicators of Program | Achieved | ||||
Health, Safety & Environment (HSE) Plan | Achieved | ||||
M0.3. Development of Manuals / Policies /Guidelines / Handbooks
| Incubator Facility Guideline/Handbook for Startups and Management Team
| Achieved | |||
Health, Safety & Environment (HSE) Manual
| Achieved | ||||
M0.4. Development and finalization of reporting Formats.
| Templates of financial, technical, progress, annual and audit reports and any other report mentioned in the contract.
| Achieved | |||
Template of Contract with startups
| Achieved | ||||
M0.5. Hiring of Project Management Team
| Report on hiring encompassing following but not limited to: Hiring procedure, JDs, Job Advertisement, Interview details, selection criteria. Selection committee and selection interview minutes | Achieved | |||
M0.6. Develop a Web Portal | Report on Web portal development | Achieved |
SR |
Quarter |
Duration |
Milestone |
Deliverable |
Status |
02
|
Y1 Q1 |
Nov 22 – Feb 23 |
M1.1. Inaugural Ceremony
M1.2. Promotion, Outreach, Selection & Induction of Cohort 1
M1.3. Seminars/Workshops/Training sessions
M1.4. Development/finalization of Curriculum & Program Schedule |
D1.1. Detailed Report on Inaugural Ceremony
D1.2. Comprehensive reports on following: 1. Advertisements/Promotions/Outreach material & statistics 2. Selection criteria and list of Judging Panel 3. Selection Criteria of startups 4. ToRs/Composition/Minutes of the Selection Panel Meeting 5. List of applicants – accepted and rejected 6. Copies of all accepted and rejected application Forms 7. Selected startups with following detail, inter alia: a) Startup Joining report b) Startup Team details c) Business Plan d) Development Plan e) Startup Genre f) Registered age of the Startup if applicable g) Success Indicators/KPI 8. Agreement between NIC and Selected Startup and copies of agreements
D1.3. Comprehensive reports on following: 1. Orientation Session of Cohort 1 2. Seminars/Workshop/Training Session Report 3. List of Mentors, Speakers, Investors & etc. and their profiles 4. Latching of Mentors with startups, if any
5. Exposure visits summary
D1.4. Comprehensive reports on following: 1. Training Program Curriculum/Content 2. Training Schedule 3. Trainers list and profile |
Achieved
Achieved Achieved Achieved Achieved Achieved Achieved Achieved Achieved Achieved Achieved Achieved Achieved Achieved Achieved Achieved Achieved |